As per the safe deployment mandate, all the configuration changes are treated as code changes. Consequently, they use similar deployment processes.
All changes that are checked in to the dev branch will be deployed in the following order: Dogfood -> RC -> MPAC -> PROD -> National Clouds (FairFax, Mooncake and BlackForest). The following table specifies the amount of time allowed to complete the deployment.
Environment | Service Level Agreement |
---|---|
DOGFOOD | 1-2 business days |
RC | 1-3 business days |
MPAC | 1-3 business days |
PROD | 5-7 business days |
FAIRFAX | Prod + 3 business days |
MOONCAKE | Prod + 6 business days |
BLACKFOREST | Prod + 9 business days |
Environment | Service Level Agreement |
---|---|
DOGFOOD | 1-2 business days |
MPAC | 1-3 business days |
PROD | 5-7 business days |
FAIRFAX | Prod + 3 business days |
MOONCAKE | Prod + 6 business days |
BLACKFOREST | Prod + 9 business days |