MVP
Past due by 10 months
90% complete
The project has reached proof of concept stage, this milestone is to closely track progress of MVP. Tracking issue: #17
Goals of MVP
- Validate the feasibility and utility of the data exchange service.
- Gather early feedback from key users and identify areas for improvement.
- Identify unforeseen challenges or limitations that arise during development.
Scope…
The project has reached proof of concept stage, this milestone is to closely track progress of MVP. Tracking issue: #17
Goals of MVP
- Validate the feasibility and utility of the data exchange service.
- Gather early feedback from key users and identify areas for improvement.
- Identify unforeseen challenges or limitations that arise during development.
Scope outside of MVP
- Advanced dispute resolution mechanisms: this may live on Horizon
- Optimal service and price matching algorithms: conduct Economics research on information markets, building on top of this paper
- Formal verifications on data validation and integrity checks.
- Detailed and polished user interface.
Post-MVP Developments
Once the MVP is successfully developed, tested, and validated, subsequent iterations would focus on
- refining the existing features,
- adding the advanced features,
- optimizing performance,
- enhancing security,
- and improving user experience based on feedback and requirements.